Chennai Metro Phase 2: what it means for offices and warehouses (October 2026)

Which business districts the new lines reach, what's open today, and what's still being built.

Updated 20 Oct 2026By S N Enterprises5 min read

In short

  • Phase I runs about 54 km: Wimco Nagar to the airport, and Central to St Thomas Mount.
  • The first Phase II stretch, Poonamallee Bypass to Vadapalani (about 15 km, 11 stations), opened on 11 October 2026.
  • Phase II's three lines add 118.9 km and 128 stations. CMRL expects to finish by the end of 2028.
  • The OMR line is under construction: track is down from Nehru Nagar to Karapakkam, but CMRL hasn't given an opening date.
In this guide
  1. What's open today
  2. The three Phase II lines
  3. If you're choosing an office or warehouse
  4. Questions

What's open today

Phase I is 45 km on two lines: Washermenpet to the airport (23.1 km) and Chennai Central to St Thomas Mount (22 km), with 32 stations. Its extension from Washermenpet to Wimco Nagar (9.05 km, 9 stations) opened in 2021 and 2022.

On 11 October 2026 the first stretch of Phase II opened: Poonamallee Bypass to Vadapalani on Corridor 4, about 15 km of elevated line with 11 stations, running 7 am to 9 pm from the next day:

  • Poonamallee Bypass, Poonamallee Bus Stand, Poonamallee Govt Hospital
  • Karayanchavadi, Kumananchavadi, Kattupakkam, Iyyappanthangal, Thelliyaragaram
  • Porur Bypass, Porur Junction, Vadapalani

Some stations between Porur and Vadapalani were reported to be left out of the first opening. Check a station's status on CMRL's site before counting on it.

The three Phase II lines

LineRouteLengthStationsBusiness areas on the way
Corridor 3Madhavaram to SIPCOT (Siruseri)45.8 km50The city centre, then OMR: Perungudi, Thoraipakkam, Karapakkam to SIPCOT
Corridor 4Lighthouse to Poonamallee Bypass26.1 km30Kodambakkam, Vadapalani, Porur, Poonamallee
Corridor 5Madhavaram to Sholinganallur47.0 km48Villivakkam, Anna Nagar, St Thomas Mount, Sholinganallur

Together they make Phase II 118.9 km and 128 stations, at ₹63,246 crore, and take the network to about 173 km. In August 2026 the government told Parliament the work was 54.62% complete.

On OMR, Corridor 3's track is laid for about 10.5 km from Nehru Nagar to Karapakkam. CMRL's own target for all of Phase II is the end of 2028; an earlier government release said 2027. Neither gives a date for OMR on its own.

If you're choosing an office or warehouse

  • A station under construction isn't a station. Plan your team's commute on what runs today, and treat the rest as a bonus when it comes.
  • Measure the walk. A building "near the metro" can be 1.5 km away by road. Walk it at office hours.
  • Expect the works. Elevated stretches mean barricades and diversions for years; ask how the building's entrance and parking are affected.
  • The new western line serves Vadapalani, Porur and Poonamallee: see offices in Vadapalani, Kodambakkam, and warehouses in Porur and Poonamallee.
  • OMR offices are a commute by road for now: see offices on OMR.

Spaces SNE has now

See all

Questions

Is there a metro on OMR yet?

Not yet. Corridor 3 is being built along OMR, and the track is down from Nehru Nagar to Karapakkam, but CMRL hasn't given an opening date. The MRTS suburban line already serves Perungudi and Taramani.

Which metro line reaches Porur?

Corridor 4, open since 11 October 2026, with stations at Porur Bypass and Porur Junction.

When will Phase II be finished?

CMRL says by the end of 2028. Its first stretch, Poonamallee Bypass to Vadapalani, is already running.